Realizations

Construction of production hall with NDT system

Project specifications
Area 2,800 m²
Completion time Four months
Team 20 people (fitters, welders, electricians, NDT specialists)
Structure Steel with reinforced concrete elements
NDT system Radiography, ultrasound, visual inspection

About the project

Project characteristics

We were invited to comprehensively build a new production hall with the implementation of a permanent NDT (non-destructive testing) quality control system. The project opened up completely new production and export opportunities for the client. It was a key investment for the development of the company

Scope of work

Implementation stages

Foundations, columns, girders, roof. Installation of the supporting structure of the hall according to the project.
Setting up machines, connecting systems, assembling internal transport.
Switchgear, main power, emergency systems, lighting.
Installation of radiographic and ultrasonic testing equipment. Calibration of equipment, trial tests.
Impart knowledge of NDT system operation, safety procedures, diagnostics.

Challenges and solutions

Design challenges and their solutions

Request a project quote

Coordination of multiple suppliers

There were several subcontractors working on the construction site. Synchronization of activities and deadlines was crucial.

Integration of a complex NDT system

The NDT system had to work with the production lines. This required precise calibration and testing

Maintaining a high level of security

The intensive assembly work required strict adherence to health and safety procedures at every stage.

Weekly coordination meetings

We held regular meetings with the client's team and subcontractors. Everyone knew what was going on.

Approval of stages by the quality inspector

Each stage of the NDT installation was approved by the inspector. We avoided corrections and delays.

Parallel work

We took advantage of our team's experience and our own assembly equipment. We worked in parallel in different areas of the hall.

Effect

End results

Facility handed over on time

After an external audit, the hall was approved for production without any amendments.

NDT system works flawlessly

Operators are trained in both operation and safety. The customer has gained confidence in quality.

New export contracts

The client gained certificates that allowed it to establish new export contracts.

Confidence confirmed by another order

A few months later, the client commissioned us to modernize a second production hall.